Traffic Information
  • 3 minutes from MRT Wenxin Forest Park Station
  • 15 minutes from HSR Taichung Station
  • 20 minutes from TRA Taichung Station
  • 30 minutes from Taichung International Airport

*All specs and certificates are subject to the actual info provided by each data center.

Facility
Building 1,058+ sq. meter of building. 10 floors and 2 underground floors of data center building.
Capacity 200 racks
Floor Loading 1,000 kg/m2
Seismic Rating 338gal
Raised Floor Height 35~50cm
Rack Size 45U (120cm x 60cm) / 42U (90cm x 60cm)
Power
Generator N+1
UPS 2N
Power Provision Support 2-4KW primary and redundant configurations for standard racks.
Fuel Storage 48 hours (depends on the loading)
Rack PDU Spec NEMA L5-20R/L6-30R
Security
Security Officers 7x24
Cameras 24-hour surveillance video, 6 months for entrance and exit images, 3 months for other images
Access Control Key cards and biometric scanners
Fire Detection VESDA
Fire Suppression NAF
Connectivity & Service
Networks HiNet backbone nodes
Diversity 1 entry point with single in-building path
Carrier Availability Project application
Cloud Access N/A
Smart Hands 7x24